New surfaces, plaster New surfaces, concrete Surfaces with old paint Suprafete noi, tencuite Surfaces with old paint Priming indoor and outdoor surfaces Protection systems

Exterior new surfaces, plaster

These surfaces should be smoothed using pumice, sandstone, hardest burnt brick or a piece of spruce plank, by circular movements; for large surfaces, electrical equipment will be used.
The existing cracks should be opened using a knife and will be repaired using fast setting cement paste.
Check and remove hollow plaster completely as necessary; small areas can be repaired using fast setting cement paste; for large areas use the same type of mortar as existing plaster.
After complete drying, smooth respective area and remove dust.
While carrying repair or re-plastering work, the substrate temperature must be at least 5°C.
Fresh plaster must dry and set for at least 7 days (according to its thickness) before applying finish.

 